2015-04-27 - 18778 - Service Request - Remove old planned orders not required #ProductionBreakFix #MMPPSupport
2015-04-27 - 18778 - Service Request - Remove old planned orders not required
Problem Summary
Remove old planned orders not required
Admin Info
Purpose
|
Remove old planned orders not required
|
Requested by
|
Babu Lankipalli
|
Issue Date
|
04-27-2015
|
Resolved by
|
Laxman
|
Resolved Date
|
04-29-2015
|
Document Status
|
Complete
|
Detailed Problem Description
(Include Screen Shots if required )
Users are claiming that below given planned orders/ purchase requisitions are created extra and need to be deleted.
Solution Analysis and Recommendations
(Include Screen Shots if required)
User are claiming that for the above materials MRP generated extra proposals. Then analyzed the MRP results and stock requirements of above materials and calculated the demand and understand that there is no extra proposals for the given material.
Resolution
The same thing conveyed and explained MRP calculations.
Release Information
Provide link here to Release Notes if Technical Objects were changed